the fencing consists of 3 panels 4 posts and 4 spikes
If done by hand,
Digging four holes with a post hole digger
Leveling the posts and attaching the fence would take about 1/2 a day on site.
I would charge you around roughly 150 plus materials.
If the panels were taller than 4-5 feet a bit more.
having to dig deeper holes to prevent a freeze from shifting the posts a bit more even.
And if necessary/having to mix and pour concrete? (by hand)
Worst case scenario 200-300 and that would be something like a 6 foot stockade, pouring concrete and having to dig 4 foot holes.
What I was taught was, you double the price of the material and add thirty percent extra for labor. That was a long time ago,but I think that sounds fair to me.
Copyright © 2024 1QUIZZ.COM - All rights reserved.
Answers & Comments
Verified answer
If done by hand,
Digging four holes with a post hole digger
Leveling the posts and attaching the fence would take about 1/2 a day on site.
I would charge you around roughly 150 plus materials.
If the panels were taller than 4-5 feet a bit more.
having to dig deeper holes to prevent a freeze from shifting the posts a bit more even.
And if necessary/having to mix and pour concrete? (by hand)
Worst case scenario 200-300 and that would be something like a 6 foot stockade, pouring concrete and having to dig 4 foot holes.
What I was taught was, you double the price of the material and add thirty percent extra for labor. That was a long time ago,but I think that sounds fair to me.